# NEC ECC: Can you have different fee percentages for different costs

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-can-you-have-different-fee-percentages-for-different-costs/4915>\
**Category:** SOCC SSOCC\
**Created:** [6 February 2019 18:48 UTC](https://reachback.builtintelligence.com/t/nec-ecc-can-you-have-different-fee-percentages-for-different-costs/4915 "2019-02-06T18:48:55Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![steverobinson](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/steverobinson/32/61_2.png) [@steverobinson](https://reachback.builtintelligence.com/u/steverobinson)\
**Post date:** [6 February 2019 18:48 UTC](https://reachback.builtintelligence.com/t/nec-ecc-can-you-have-different-fee-percentages-for-different-costs/4915/1 "2019-02-06T18:48:55Z")

</div>

Under Option C can you have two Fee Percentages for the different Fee Percentages to apply to different sections from the Schedule of cost components, i.e. a % for Section 1, People and a % for all other sections of the Schedule of Cost Components.

Under CD Part 2 only one fee percentage can be stated

---

<div class="post-metadata">

**Author:** ![Glenn\_Hide](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/glenn_hide/32/476_2.png) [@Glenn\_Hide](https://reachback.builtintelligence.com/u/Glenn_Hide)\
**Post date:** [6 February 2019 19:04 UTC](https://reachback.builtintelligence.com/t/nec-ecc-can-you-have-different-fee-percentages-for-different-costs/4915/2 "2019-02-06T19:04:52Z")

</div>

This is now a different answer depending if you are working under NEC3 or NEC4

For NEC3, you have a subcontract fee percentage (to be applied to all subcontractor costs) and direct fee percentage (for everything else). You also have a working area percentage (options C-E) and people percentage (options A-B) which is applied to your people costs within section 1 of the SCC, before direct fee/subcontract fee is applied to the total of all the other amounts.

For NEC4, there is now only one fee to cover the equivalent of Subcontract fee/direct fee/people overhead/working area.