# JCT Sub-Contract

**URL:** https://reachback.builtintelligence.com/t/jct-sub-contract/22626
**Category:** General
**Created:** [28 April 2026 17:26 UTC](https://reachback.builtintelligence.com/t/jct-sub-contract/22626 "2026-04-28T17:26:42Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![jim823408](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jim823408/32/1424_2.png) [@jim823408](https://reachback.builtintelligence.com/u/jim823408)
#### Post date: [28 April 2026 17:26 UTC](https://reachback.builtintelligence.com/t/jct-sub-contract/22626/1 "2026-04-28T17:26:42Z")

</div>

Hi

I wonder if anyone could answer the following tricky query for me relating to the JCT DB Sub-Contract (DBSub/2016).

The Sub-Contract Particulars make provision at para 5 for splitting the Sub-Contract Works into “Sections” (whereby a period is stated for each Section).

However, can I spit the Sub-Contract Works into formal “Sections” in the Sub-Contract Particulars if the Main Contract Works are not split into Sections (i.e. a single Date of Possession and Date for Completion apply for the Main Contract Works)?

It seems not because clause 1.1 of the Sub-Contract Conditions defines the word “Section” by reference to the Main Contract, or have I interpreted this incorrectly?

I’d be very grateful for any feedback on this.

Thanks

---

<div class="post-metadata">

### Author: ![Mike\_Tiplady](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/mike_tiplady/32/516_2.png) [@Mike\_Tiplady](https://reachback.builtintelligence.com/u/Mike_Tiplady)
#### Post date: [29 April 2026 10:21 UTC](https://reachback.builtintelligence.com/t/jct-sub-contract/22626/2 "2026-04-29T10:21:57Z")

</div>

The JCT Sub-Contract relies upon the Main Contract to define Sections so if there are none in the Main Contract then there are none in the Sub-Contract. However that would not prevent you from seeking to amend the Sub-Contract to allow for sections. Some drafting would need to be included in the Sub-Contract Agreement to that effect.