# JCT DB 2016 Material on site procedure

**URL:** <https://reachback.builtintelligence.com/t/jct-db-2016-material-on-site-procedure/14843>\
**Category:** JCT Contracts\
**Created:** [19 May 2021 09:44 UTC](https://reachback.builtintelligence.com/t/jct-db-2016-material-on-site-procedure/14843 "2021-05-19T09:44:25Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BR\_2021](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/br_2021/32/178_2.png) [@BR\_2021](https://reachback.builtintelligence.com/u/BR_2021)\
**Post date:** [19 May 2021 09:44 UTC](https://reachback.builtintelligence.com/t/jct-db-2016-material-on-site-procedure/14843/1 "2021-05-19T09:44:25Z")

</div>

Under the JCT DB 2016, does the sub-contractor have to provide invoices/ delivery notes for material on site he is claiming in a monthly application?

---

<div class="post-metadata">

**Author:** ![dmacdonald](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/dmacdonald/32/181_2.png) [@dmacdonald](https://reachback.builtintelligence.com/u/dmacdonald)\
**Post date:** [4 June 2021 18:47 UTC](https://reachback.builtintelligence.com/t/jct-db-2016-material-on-site-procedure/14843/2 "2021-06-04T18:47:36Z")

</div>

No. But the more evidence you can provide the less opportunity the MC had to amend your application