# JCT DB 2016 Corresponding Subcontract

**URL:** <https://reachback.builtintelligence.com/t/jct-db-2016-corresponding-subcontract/18285>\
**Category:** JCT Contracts\
**Created:** [27 July 2022 14:17 UTC](https://reachback.builtintelligence.com/t/jct-db-2016-corresponding-subcontract/18285 "2022-07-27T14:17:28Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![paulob](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/paulob/32/75_2.png) [@paulob](https://reachback.builtintelligence.com/u/paulob)\
**Post date:** [27 July 2022 14:17 UTC](https://reachback.builtintelligence.com/t/jct-db-2016-corresponding-subcontract/18285/1 "2022-07-27T14:17:28Z")

</div>

When the main contract is a 2016 DB what would be the most appropriate subcontract where the subcontractor has no design responsibility. Subcontract to be on a lump sum basis?

---

<div class="post-metadata">

**Author:** ![Mike\_Tiplady](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/mike_tiplady/32/516_2.png) [@Mike\_Tiplady](https://reachback.builtintelligence.com/u/Mike_Tiplady)\
**Post date:** [27 July 2022 14:40 UTC](https://reachback.builtintelligence.com/t/jct-db-2016-corresponding-subcontract/18285/2 "2022-07-27T14:40:00Z")

</div>

Paul. You would want to use the JCT 2016 DBSub/A and DBSub/C conditions of contract. You would delete the Third Recital and use Article 3A (deleting Article 3B for re-measurement). If you need help putting the Sub-Contract together please obtain proper advice.