# JCT D&B SFC Time at large

**URL:** <https://reachback.builtintelligence.com/t/jct-d-b-sfc-time-at-large/15112>\
**Category:** General\
**Created:** [1 July 2021 11:44 UTC](https://reachback.builtintelligence.com/t/jct-d-b-sfc-time-at-large/15112 "2021-07-01T11:44:15Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![liz\_exley](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/liz_exley/32/623_2.png) [@liz\_exley](https://reachback.builtintelligence.com/u/liz_exley)\
**Post date:** [1 July 2021 11:44 UTC](https://reachback.builtintelligence.com/t/jct-d-b-sfc-time-at-large/15112/1 "2021-07-01T11:44:15Z")

</div>

Surely the JCT D&B SFC includes mechanism for extending time due to reasons attributable to Employer =\> in what circumstances would time be at large?

---

<div class="post-metadata">

**Author:** ![Mike\_Tiplady](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/mike_tiplady/32/516_2.png) [@Mike\_Tiplady](https://reachback.builtintelligence.com/u/Mike_Tiplady)\
**Post date:** [28 November 2023 16:48 UTC](https://reachback.builtintelligence.com/t/jct-d-b-sfc-time-at-large/15112/2 "2023-11-28T16:48:13Z")

</div>

Very unlikely that there would ever be a time at large scenario because that would leave the Contractor to undertake and complete the Works whenever it suited him/her. At best there could be a situation where the Contractor, rather than having a specified date by which to complete; had a reasonable period of time in which to complete. That is hugely different to time at large.