Is there provision in the ECC3 to "decelerate" works at the Employer's behest

1 Like

Not explicitly.

However, the Project Manager can give an instruction “to stop or not to start any work” and then re-start it later. Alternatively, they can change the Works Information to impose additional constraints which have the effect of slowing work down.

Both of these approaches result in a compensation event.