# Is it legally permissible for employers to pay sub-contractors directly should they be experiencing financial difficulties?

**URL:** <https://reachback.builtintelligence.com/t/is-it-legally-permissible-for-employers-to-pay-sub-contractors-directly-should-they-be-experiencing-financial-difficulties/2308>\
**Category:** JCT Contracts\
**Created:** [5 February 2013 14:59 UTC](https://reachback.builtintelligence.com/t/is-it-legally-permissible-for-employers-to-pay-sub-contractors-directly-should-they-be-experiencing-financial-difficulties/2308 "2013-02-05T14:59:49Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![JCT\_Experts](https://avatars.discourse-cdn.com/v4/letter/j/eb9ed0/32.png) [@JCT\_Experts](https://reachback.builtintelligence.com/u/JCT_Experts)\
**Post date:** [5 February 2013 14:59 UTC](https://reachback.builtintelligence.com/t/is-it-legally-permissible-for-employers-to-pay-sub-contractors-directly-should-they-be-experiencing-financial-difficulties/2308/1 "2013-02-05T14:59:49Z")

</div>



---

<div class="post-metadata">

**Author:** ![JCT\_Experts](https://avatars.discourse-cdn.com/v4/letter/j/eb9ed0/32.png) [@JCT\_Experts](https://reachback.builtintelligence.com/u/JCT_Experts)\
**Post date:** [5 February 2013 15:00 UTC](https://reachback.builtintelligence.com/t/is-it-legally-permissible-for-employers-to-pay-sub-contractors-directly-should-they-be-experiencing-financial-difficulties/2308/2 "2013-02-05T15:00:27Z")

</div>

Although this has previously occurred, there are no such provisions in JCT Standard Building Contract 2009 and no nominated subcontractors within it.