# Is a contractor obligated to draw attention to errors within an architect's drawing?

**URL:** <https://reachback.builtintelligence.com/t/is-a-contractor-obligated-to-draw-attention-to-errors-within-an-architects-drawing/2210>\
**Category:** JCT Contracts\
**Created:** [4 February 2013 14:59 UTC](https://reachback.builtintelligence.com/t/is-a-contractor-obligated-to-draw-attention-to-errors-within-an-architects-drawing/2210 "2013-02-04T14:59:40Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![JCT\_Experts](https://avatars.discourse-cdn.com/v4/letter/j/eb9ed0/32.png) [@JCT\_Experts](https://reachback.builtintelligence.com/u/JCT_Experts)\
**Post date:** [4 February 2013 14:59 UTC](https://reachback.builtintelligence.com/t/is-a-contractor-obligated-to-draw-attention-to-errors-within-an-architects-drawing/2210/1 "2013-02-04T14:59:40Z")

</div>



---

<div class="post-metadata">

**Author:** ![JCT\_Experts](https://avatars.discourse-cdn.com/v4/letter/j/eb9ed0/32.png) [@JCT\_Experts](https://reachback.builtintelligence.com/u/JCT_Experts)\
**Post date:** [4 February 2013 15:00 UTC](https://reachback.builtintelligence.com/t/is-a-contractor-obligated-to-draw-attention-to-errors-within-an-architects-drawing/2210/2 "2013-02-04T15:00:27Z")

</div>

Generally speaking, a contractor has no obligation nor liability for design. However, a court may take a dim view of a contractor entering into work while explicitly being aware that there were significant design errors within a project. Of course, such a verdict would have to be made on an evidential basis, and proving such a thing could be fraught with difficulty.