# If the Employer has chosen a secondary option, where in the contract is it mentioned?

**URL:** <https://reachback.builtintelligence.com/t/if-the-employer-has-chosen-a-secondary-option-where-in-the-contract-is-it-mentioned/849>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 11:08 UTC](https://reachback.builtintelligence.com/t/if-the-employer-has-chosen-a-secondary-option-where-in-the-contract-is-it-mentioned/849 "2012-10-16T11:08:20Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 11:08 UTC](https://reachback.builtintelligence.com/t/if-the-employer-has-chosen-a-secondary-option-where-in-the-contract-is-it-mentioned/849/1 "2012-10-16T11:08:20Z")

</div>

If the Employer has chosen a secondary option, where in the contract is it mentioned?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 11:08 UTC](https://reachback.builtintelligence.com/t/if-the-employer-has-chosen-a-secondary-option-where-in-the-contract-is-it-mentioned/849/2 "2012-10-16T11:08:33Z")

</div>

The chosen secondary Options, together with the chosen main Option, must be identified in the first statement of part one of the Contract Data.