# If I am a designer working for a domestic client, do I have to comply with the CDM Regulations?

**URL:** <https://reachback.builtintelligence.com/t/if-i-am-a-designer-working-for-a-domestic-client-do-i-have-to-comply-with-the-cdm-regulations/1337>\
**Category:** CDM\
**Created:** [13 January 2013 10:03 UTC](https://reachback.builtintelligence.com/t/if-i-am-a-designer-working-for-a-domestic-client-do-i-have-to-comply-with-the-cdm-regulations/1337 "2013-01-13T10:03:55Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [13 January 2013 10:03 UTC](https://reachback.builtintelligence.com/t/if-i-am-a-designer-working-for-a-domestic-client-do-i-have-to-comply-with-the-cdm-regulations/1337/1 "2013-01-13T10:03:55Z")

</div>



---

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [24 January 2013 13:25 UTC](https://reachback.builtintelligence.com/t/if-i-am-a-designer-working-for-a-domestic-client-do-i-have-to-comply-with-the-cdm-regulations/1337/2 "2013-01-24T13:25:12Z")

</div>

Yes. You will need to comply with the duties placed on designers in Parts 1 and 2 of the Regulations. (There are no duties on designers in Part 4.)