# How much are the low performance damages included in the Contract Data?

**URL:** <https://reachback.builtintelligence.com/t/how-much-are-the-low-performance-damages-included-in-the-contract-data/980>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 15:40 UTC](https://reachback.builtintelligence.com/t/how-much-are-the-low-performance-damages-included-in-the-contract-data/980 "2012-10-16T15:40:37Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 15:40 UTC](https://reachback.builtintelligence.com/t/how-much-are-the-low-performance-damages-included-in-the-contract-data/980/1 "2012-10-16T15:40:37Z")

</div>

How much are the low performance damages included in the Contract Data?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 15:41 UTC](https://reachback.builtintelligence.com/t/how-much-are-the-low-performance-damages-included-in-the-contract-data/980/2 "2012-10-16T15:41:09Z")

</div>

The low performance damages applicable within secondary option X7 if included in the Contract Data should be a genuine pre-estimate of the actual damages that the Employer will suffer as a result of the Contractor’s breach. They will be identified in Contract Data part 1 at tender stage as the price per day for exceeding the Completion Date and also any Sectional Completion Dates if X5 has also been used. The Contractor can/should therefore price any associated risk within their price.

We have seen them vary from £1/day, where the Employer was making it clear that any overrun would not be a Contractor risk (and hence reflected a cheaper tender price) to £60.000/day on the likes of Crossrail projects.