# How long does the Contractor have to submit a revised quotation for dealing with a compensation event?

**URL:** <https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/113>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:16 UTC](https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/113 "2012-10-09T20:16:00Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:16 UTC](https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/113/1 "2012-10-09T20:16:00Z")

</div>

How long does the Contractor have to submit a revised quotation for dealing with a compensation event?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:16 UTC](https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-revised-quotation-for-dealing-with-a-compensation-event/113/2 "2012-10-09T20:16:22Z")

</div>

The Contractor submits the revised quotation within three weeks of being instructed to do so by the Project Manager (see clause 62.4).