# How long does the Contractor have to submit a quotation for acceleration?

**URL:** <https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-quotation-for-acceleration/563>\
**Category:** Time\
**Created:** [14 October 2012 19:25 UTC](https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-quotation-for-acceleration/563 "2012-10-14T19:25:47Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:25 UTC](https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-quotation-for-acceleration/563/1 "2012-10-14T19:25:47Z")

</div>

How long does the Contractor have to submit a quotation for acceleration?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:25 UTC](https://reachback.builtintelligence.com/t/how-long-does-the-contractor-have-to-submit-a-quotation-for-acceleration/563/2 "2012-10-14T19:25:58Z")

</div>

The Contractor submits a quotation or gives his reasons for not doing so within the period for reply (see Clause 36.2).