# How is the Shorter Schedule of Cost Components used in Option D?

**URL:** https://reachback.builtintelligence.com/t/how-is-the-shorter-schedule-of-cost-components-used-in-option-d/1073
**Category:** SOCC SSOCC
**Created:** [16 November 2012 15:06 UTC](https://reachback.builtintelligence.com/t/how-is-the-shorter-schedule-of-cost-components-used-in-option-d/1073 "2012-11-16T15:06:57Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)
#### Post date: [16 November 2012 15:06 UTC](https://reachback.builtintelligence.com/t/how-is-the-shorter-schedule-of-cost-components-used-in-option-d/1073/1 "2012-11-16T15:06:57Z")

</div>

How is the Shorter Schedule of Cost Components used in Option D?

---

<div class="post-metadata">

### Author: ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)
#### Post date: [16 November 2012 15:07 UTC](https://reachback.builtintelligence.com/t/how-is-the-shorter-schedule-of-cost-components-used-in-option-d/1073/2 "2012-11-16T15:07:06Z")

</div>

It can be used: to assess a compensation event even if the Project Manager and the Contractor are in agreement; or by the Project Manager when he is making his own assessments of a compensation event.