# How is a delay to a Key Date assessed?

**URL:** <https://reachback.builtintelligence.com/t/how-is-a-delay-to-a-key-date-assessed/119>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:22 UTC](https://reachback.builtintelligence.com/t/how-is-a-delay-to-a-key-date-assessed/119 "2012-10-09T20:22:42Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:22 UTC](https://reachback.builtintelligence.com/t/how-is-a-delay-to-a-key-date-assessed/119/1 "2012-10-09T20:22:42Z")

</div>

How is a delay to a Key Date assessed?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:23 UTC](https://reachback.builtintelligence.com/t/how-is-a-delay-to-a-key-date-assessed/119/2 "2012-10-09T20:23:04Z")

</div>

A delay to a Key Date is assessed as the length of time that, due to the compensation event, the planned date when the Condition stated for a Key Date will be met is later than the date shown on the Accepted Programme (see clause 63.3).