# How is a compensation event handled if, when the Contractor submits quotations for a compensation event, he has not submitted a programme or alterations to a programme which the contract requires him to submit?

**URL:** https://reachback.builtintelligence.com/t/how-is-a-compensation-event-handled-if-when-the-contractor-submits-quotations-for-a-compensation-event-he-has-not-submitted-a-programme-or-alterations-to-a-programme-which-the-contract-requires-him-to-submit/129
**Category:** Compensation Events
**Created:** [9 October 2012 20:35 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-handled-if-when-the-contractor-submits-quotations-for-a-compensation-event-he-has-not-submitted-a-programme-or-alterations-to-a-programme-which-the-contract-requires-him-to-submit/129 "2012-10-09T20:35:13Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [9 October 2012 20:35 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-handled-if-when-the-contractor-submits-quotations-for-a-compensation-event-he-has-not-submitted-a-programme-or-alterations-to-a-programme-which-the-contract-requires-him-to-submit/129/1 "2012-10-09T20:35:13Z")

</div>

How is a compensation event handled if, when the Contractor submits quotations for a compensation event, he has not submitted a programme or alterations to a programme which the contract requires him to submit?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [9 October 2012 20:35 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-handled-if-when-the-contractor-submits-quotations-for-a-compensation-event-he-has-not-submitted-a-programme-or-alterations-to-a-programme-which-the-contract-requires-him-to-submit/129/2 "2012-10-09T20:35:42Z")

</div>

The Project Manager will assess the compensation event (see Clause 64.1).