# How is a compensation event assessed if there is no accepted programme?

**URL:** <https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-there-is-no-accepted-programme/131>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:37 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-there-is-no-accepted-programme/131 "2012-10-09T20:37:39Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:37 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-there-is-no-accepted-programme/131/1 "2012-10-09T20:37:39Z")

</div>

How is a compensation event assessed if there is no accepted programme?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:38 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-there-is-no-accepted-programme/131/2 "2012-10-09T20:38:13Z")

</div>

The Project Manager assesses the event using his own assessment for the remaining work (see Clause 64.2).