# How is a compensation event assessed if the Contractor has not submitted a programme or alterations to a programme for acceptance as required by the contract?

**URL:** <https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-the-contractor-has-not-submitted-a-programme-or-alterations-to-a-programme-for-acceptance-as-required-by-the-contract/132>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:38 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-the-contractor-has-not-submitted-a-programme-or-alterations-to-a-programme-for-acceptance-as-required-by-the-contract/132 "2012-10-09T20:38:55Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:38 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-the-contractor-has-not-submitted-a-programme-or-alterations-to-a-programme-for-acceptance-as-required-by-the-contract/132/1 "2012-10-09T20:38:55Z")

</div>

How is a compensation event assessed if the Contractor has not submitted a programme or alterations to a programme for acceptance as required by the contract?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:39 UTC](https://reachback.builtintelligence.com/t/how-is-a-compensation-event-assessed-if-the-contractor-has-not-submitted-a-programme-or-alterations-to-a-programme-for-acceptance-as-required-by-the-contract/132/2 "2012-10-09T20:39:16Z")

</div>

The Project Manager assesses the event using his own assessment for the remaining work (see Clause 64.2).