# How does the Project Manager or the Contractor notify of an early warning?

**URL:** https://reachback.builtintelligence.com/t/how-does-the-project-manager-or-the-contractor-notify-of-an-early-warning/1102
**Category:** General
**Created:** [19 November 2012 14:11 UTC](https://reachback.builtintelligence.com/t/how-does-the-project-manager-or-the-contractor-notify-of-an-early-warning/1102 "2012-11-19T14:11:26Z")
**Posts on this page:** 1
**Showing post:** 2

<div class="post-metadata">

### Author: ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)
#### Post date: [19 November 2012 14:11 UTC](https://reachback.builtintelligence.com/t/how-does-the-project-manager-or-the-contractor-notify-of-an-early-warning/1102/2 "2012-11-19T14:11:54Z")

</div>

An Early Warning is a notification of a matter that could affect the price, the programme or the performance of the works.  
There is no reply per se required to an early warning notification but the parties may require the other to attend an early warning meeting (also called risk reduction meeting) if the matter required the parties’ attention immediately.  
The Contractor can be sanctioned for not raising an early warning that he could have raised.

---

_[View the full topic](https://reachback.builtintelligence.com/t/how-does-the-project-manager-or-the-contractor-notify-of-an-early-warning/1102)._