# How does the Project Manager certify the take over?

**URL:** <https://reachback.builtintelligence.com/t/how-does-the-project-manager-certify-the-take-over/1108>\
**Category:** Time\
**Created:** [19 November 2012 14:24 UTC](https://reachback.builtintelligence.com/t/how-does-the-project-manager-certify-the-take-over/1108 "2012-11-19T14:24:50Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [19 November 2012 14:24 UTC](https://reachback.builtintelligence.com/t/how-does-the-project-manager-certify-the-take-over/1108/1 "2012-11-19T14:24:50Z")

</div>

How does the Project Manager certify the take over?

---

<div class="post-metadata">

**Author:** ![Rob\_Glasspool](https://avatars.discourse-cdn.com/v4/letter/r/a88e57/32.png) [@Rob\_Glasspool](https://reachback.builtintelligence.com/u/Rob_Glasspool)\
**Post date:** [19 November 2012 14:25 UTC](https://reachback.builtintelligence.com/t/how-does-the-project-manager-certify-the-take-over/1108/2 "2012-11-19T14:25:24Z")

</div>

The Project Manager has decided the date of Completion and has certified Completion within one week of the completion  
The Employer takes over the works not more than two weeks after completion. This may refer to Completion of a section or Completion of the whole of the works.  
Possession/access of each part of the Site taken over returns to the Employer at take over.  
The Project Manager certifies take over not more than one week after the date of take over.