# How do adjudicators keep all parties informed of the adjudication process?

**URL:** <https://reachback.builtintelligence.com/t/how-do-adjudicators-keep-all-parties-informed-of-the-adjudication-process/1490>\
**Category:** Adjudication\
**Created:** [18 January 2013 09:35 UTC](https://reachback.builtintelligence.com/t/how-do-adjudicators-keep-all-parties-informed-of-the-adjudication-process/1490 "2013-01-18T09:35:10Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 09:35 UTC](https://reachback.builtintelligence.com/t/how-do-adjudicators-keep-all-parties-informed-of-the-adjudication-process/1490/1 "2013-01-18T09:35:10Z")

</div>



---

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 09:35 UTC](https://reachback.builtintelligence.com/t/how-do-adjudicators-keep-all-parties-informed-of-the-adjudication-process/1490/2 "2013-01-18T09:35:32Z")

</div>

By issuing a timetable by which submissions are to be made and possibly fixing a provisional date for a meeting.