# Does the Employer take over the works before the Completion Date?

**URL:** <https://reachback.builtintelligence.com/t/does-the-employer-take-over-the-works-before-the-completion-date/556>\
**Category:** Time\
**Created:** [14 October 2012 19:20 UTC](https://reachback.builtintelligence.com/t/does-the-employer-take-over-the-works-before-the-completion-date/556 "2012-10-14T19:20:20Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:20 UTC](https://reachback.builtintelligence.com/t/does-the-employer-take-over-the-works-before-the-completion-date/556/1 "2012-10-14T19:20:20Z")

</div>

Does the Employer take over the works before the Completion Date?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:20 UTC](https://reachback.builtintelligence.com/t/does-the-employer-take-over-the-works-before-the-completion-date/556/2 "2012-10-14T19:20:32Z")

</div>

The Employer does not have to take over the works before the Completion Date if it is stated in the Contract Data that he is not willing to do so (see Clause 35.1).