# Does the Contractor require the Project Manager’s permission to remove Plant or Materials?

**URL:** <https://reachback.builtintelligence.com/t/does-the-contractor-require-the-project-manager-s-permission-to-remove-plant-or-materials/630>\
**Category:** Title\
**Created:** [15 October 2012 12:18 UTC](https://reachback.builtintelligence.com/t/does-the-contractor-require-the-project-manager-s-permission-to-remove-plant-or-materials/630 "2012-10-15T12:18:58Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:18 UTC](https://reachback.builtintelligence.com/t/does-the-contractor-require-the-project-manager-s-permission-to-remove-plant-or-materials/630/1 "2012-10-15T12:18:58Z")

</div>

Does the Contractor require the Project Manager’s permission to remove Plant or Materials?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 12:19 UTC](https://reachback.builtintelligence.com/t/does-the-contractor-require-the-project-manager-s-permission-to-remove-plant-or-materials/630/2 "2012-10-15T12:19:10Z")

</div>

Yes. Not to do so may result in title to said Plant and Materials remaining with the Employer.