# Does the assessment of a compensation event include an allowance for risk?

**URL:** <https://reachback.builtintelligence.com/t/does-the-assessment-of-a-compensation-event-include-an-allowance-for-risk/121>\
**Category:** Compensation Events\
**Created:** [9 October 2012 20:24 UTC](https://reachback.builtintelligence.com/t/does-the-assessment-of-a-compensation-event-include-an-allowance-for-risk/121 "2012-10-09T20:24:45Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:24 UTC](https://reachback.builtintelligence.com/t/does-the-assessment-of-a-compensation-event-include-an-allowance-for-risk/121/1 "2012-10-09T20:24:45Z")

</div>

Does the assessment of a compensation event include an allowance for risk?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [9 October 2012 20:25 UTC](https://reachback.builtintelligence.com/t/does-the-assessment-of-a-compensation-event-include-an-allowance-for-risk/121/2 "2012-10-09T20:25:26Z")

</div>

Assessment of the effect of a compensation event includes risk allowances for cost and time for matters which have a significant chance of occurring and are at the Contractor’s risk under this contract (see clause 63.6)