# Does information in the Activity Schedule count as Works Information or Site Information?

**URL:** https://reachback.builtintelligence.com/t/does-information-in-the-activity-schedule-count-as-works-information-or-site-information/661
**Category:** NEC3 and NEC4 Contracts
**Created:** [15 October 2012 13:36 UTC](https://reachback.builtintelligence.com/t/does-information-in-the-activity-schedule-count-as-works-information-or-site-information/661 "2012-10-15T13:36:30Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 13:36 UTC](https://reachback.builtintelligence.com/t/does-information-in-the-activity-schedule-count-as-works-information-or-site-information/661/1 "2012-10-15T13:36:30Z")

</div>

Does information in the Activity Schedule count as Works Information or Site Information?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 13:36 UTC](https://reachback.builtintelligence.com/t/does-information-in-the-activity-schedule-count-as-works-information-or-site-information/661/2 "2012-10-15T13:36:42Z")

</div>

No. Information in the Activity Schedule is not Works Information or Site Information (see Clause 54.1).