# CE's Issued Under 60.1 or 61.1?

**URL:** <https://reachback.builtintelligence.com/t/ces-issued-under-60-1-or-61-1/21233>\
**Category:** Compensation Events\
**Created:** [14 August 2023 23:26 UTC](https://reachback.builtintelligence.com/t/ces-issued-under-60-1-or-61-1/21233 "2023-08-14T23:26:20Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Jonathan\_Atwall](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jonathan_atwall/32/103_2.png) [@Jonathan\_Atwall](https://reachback.builtintelligence.com/u/Jonathan_Atwall)\
**Post date:** [14 August 2023 23:26 UTC](https://reachback.builtintelligence.com/t/ces-issued-under-60-1-or-61-1/21233/1 "2023-08-14T23:26:20Z")

</div>

The class is split on this one. We have been receiving CI’s under clause14.3, but then corresponding CE’s issued under clause 61.1, i.e. In accordance with Cl61.1 this is a Compensation Event’. However there is a debate ongoing as to whether the CE notice should say ‘In accordance with 60.1(1), this is a Compensation Event’. Both sound plausible. For me, 61.1 is an obligation and 60.1 states what the CE is, so more siding to 60.1, Cheers.

---

<div class="post-metadata">

**Author:** ![QS007](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/qs007/32/173_2.png) [@QS007](https://reachback.builtintelligence.com/u/QS007)\
**Post date:** [15 August 2023 15:04 UTC](https://reachback.builtintelligence.com/t/ces-issued-under-60-1-or-61-1/21233/2 "2023-08-15T15:04:10Z")

</div>

I agree with you. When a CE occurs the Contractor is ‘obligated’ under 61.1 / 61.2 to notify the compensation event, which is one tick in the box, the second tick in the box is to notify the compensation event type i.e. change to Works Information / Scope 60.1 (1).