If a potential Covid-19 case came back negative, but while waiting for THE test results the program was delayed, can a CE be raise for lost time and cost?(NEC3 Option C)
1 Like
The question is ‘what CE would it be’.
To answer that, I don’t see why you would treat this differently to someone not coming to work due to any other ailment or injury. It might result in additional costs if the person is replaced, I don’t believe this is a CE.