# Can the Project Manager instruct additional tests to those stated in the Works Information?

**URL:** <https://reachback.builtintelligence.com/t/can-the-project-manager-instruct-additional-tests-to-those-stated-in-the-works-information/576>\
**Category:** Testing and Defects\
**Created:** [14 October 2012 19:35 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-instruct-additional-tests-to-those-stated-in-the-works-information/576 "2012-10-14T19:35:07Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:35 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-instruct-additional-tests-to-those-stated-in-the-works-information/576/1 "2012-10-14T19:35:07Z")

</div>

Can the Project Manager instruct additional tests to those stated in the Works Information?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:35 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-instruct-additional-tests-to-those-stated-in-the-works-information/576/2 "2012-10-14T19:35:22Z")

</div>

Yes. He can do this by changing the Works Information. If no Defects are subsequently found however (providing it’s not a repeat test for a corrected Defect), it is a compensation event (see Clause 60.1(1))