# Can the Project Manager delegate his actions?

**URL:** <https://reachback.builtintelligence.com/t/can-the-project-manager-delegate-his-actions/436>\
**Category:** General\
**Created:** [12 October 2012 15:23 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-delegate-his-actions/436 "2012-10-12T15:23:01Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 15:23 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-delegate-his-actions/436/1 "2012-10-12T15:23:01Z")

</div>

Can the Project Manager delegate his actions?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 15:23 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-delegate-his-actions/436/2 "2012-10-12T15:23:16Z")

</div>

Yes. Clause 14.2 allows the Project Manager to delegate any of his actions after he has notified the Contractor. As such, references to the Project Manager in the contract can also extend to his delegate. The Project Manager can also cancel any such delegation.