# Can the Project Manager change the Works Information?

**URL:** <https://reachback.builtintelligence.com/t/can-the-project-manager-change-the-works-information/439>\
**Category:** General\
**Created:** [12 October 2012 15:25 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-change-the-works-information/439 "2012-10-12T15:25:15Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 15:25 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-change-the-works-information/439/1 "2012-10-12T15:25:15Z")

</div>

Can the Project Manager change the Works Information?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 15:25 UTC](https://reachback.builtintelligence.com/t/can-the-project-manager-change-the-works-information/439/2 "2012-10-12T15:25:32Z")

</div>

Yes. As stated in Clause 14.3, the Project Manager may issue an instruction to the Contractor which changes the Works Information but all changes of this nature are potentially compensation events under Clause 60.1(1).