# Can the Parties limit the total delay damages for the whole of the works?

**URL:** <https://reachback.builtintelligence.com/t/can-the-parties-limit-the-total-delay-damages-for-the-whole-of-the-works/920>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 14:11 UTC](https://reachback.builtintelligence.com/t/can-the-parties-limit-the-total-delay-damages-for-the-whole-of-the-works/920 "2012-10-16T14:11:26Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 14:11 UTC](https://reachback.builtintelligence.com/t/can-the-parties-limit-the-total-delay-damages-for-the-whole-of-the-works/920/1 "2012-10-16T14:11:26Z")

</div>

Can the Parties limit the total delay damages for the whole of the works?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 14:11 UTC](https://reachback.builtintelligence.com/t/can-the-parties-limit-the-total-delay-damages-for-the-whole-of-the-works/920/2 "2012-10-16T14:11:47Z")

</div>

Yes. If the Parties wish to limit the total delay damages for the whole of the works, the entry in the Contract Data should be amended by adding ‘with a maximum total amount payable of…’. Similar amendments should be made to the Contract Data if it is intended to place a cap on the damages for particular sections of the works where Options X5 and X7 are used together.