# Can the Employer terminate if the Contractor fails to provide a guarantee from his parent company?

**URL:** <https://reachback.builtintelligence.com/t/can-the-employer-terminate-if-the-contractor-fails-to-provide-a-guarantee-from-his-parent-company/887>\
**Category:** Secondary X, W and Y options\
**Created:** [16 October 2012 12:02 UTC](https://reachback.builtintelligence.com/t/can-the-employer-terminate-if-the-contractor-fails-to-provide-a-guarantee-from-his-parent-company/887 "2012-10-16T12:02:04Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 12:02 UTC](https://reachback.builtintelligence.com/t/can-the-employer-terminate-if-the-contractor-fails-to-provide-a-guarantee-from-his-parent-company/887/1 "2012-10-16T12:02:04Z")

</div>

Can the Employer terminate if the Contractor fails to provide a guarantee from his parent company?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [16 October 2012 12:02 UTC](https://reachback.builtintelligence.com/t/can-the-employer-terminate-if-the-contractor-fails-to-provide-a-guarantee-from-his-parent-company/887/2 "2012-10-16T12:02:19Z")

</div>

If, after four weeks of the Project Manager notifying of a default because of the Contractor’s failure to provide the guarantee, the Contractor still has not provided a guarantee from his parent company, the Employer is entitled to terminate.