# Can the Contractor proceed with the work if the Project Manager has not accepted his programme?

**URL:** <https://reachback.builtintelligence.com/t/can-the-contractor-proceed-with-the-work-if-the-project-manager-has-not-accepted-his-programme/527>\
**Category:** Time\
**Created:** [12 October 2012 18:08 UTC](https://reachback.builtintelligence.com/t/can-the-contractor-proceed-with-the-work-if-the-project-manager-has-not-accepted-his-programme/527 "2012-10-12T18:08:44Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 18:08 UTC](https://reachback.builtintelligence.com/t/can-the-contractor-proceed-with-the-work-if-the-project-manager-has-not-accepted-his-programme/527/1 "2012-10-12T18:08:44Z")

</div>

Can the Contractor proceed with the work if the Project Manager has not accepted his programme?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 18:08 UTC](https://reachback.builtintelligence.com/t/can-the-contractor-proceed-with-the-work-if-the-project-manager-has-not-accepted-his-programme/527/2 "2012-10-12T18:08:58Z")

</div>

Yes. Unlike with acceptance of the Contractor’s design, the Contractor can proceed with the works if his programme has not been accepted.