Can I recover the cost of insurance premiums under an ECC Option C?
You do not clarify exactly which insurance premiums you are referring to?
part of the direct fee percentage would be insurances for:
head office - premises and contents
Public Liability Insurance
Car Insurances
Property Insurances
Professional Indemnity Insurance
INsurances required by clause 84.2
Part of the Schedule of Cost Components SCC in relation to People
Travel Insurance
Medical Insurances
Some Employers amend the SCC or have developed their own SCC based on their experiences over the years and they will clearly identify whether the elements of cost in relation to insurances should be allocasted to the Fee or SCC