# Can any other parties change the Works Information?

**URL:** <https://reachback.builtintelligence.com/t/can-any-other-parties-change-the-works-information/440>\
**Category:** General\
**Created:** [12 October 2012 15:26 UTC](https://reachback.builtintelligence.com/t/can-any-other-parties-change-the-works-information/440 "2012-10-12T15:26:17Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 15:26 UTC](https://reachback.builtintelligence.com/t/can-any-other-parties-change-the-works-information/440/1 "2012-10-12T15:26:17Z")

</div>

Can any other parties change the Works Information?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 15:26 UTC](https://reachback.builtintelligence.com/t/can-any-other-parties-change-the-works-information/440/2 "2012-10-12T15:26:42Z")

</div>

Only the Project Manager and a person to whom he has delegated this authority may change the Works Information. Neither the Employer, Supervisor nor the Adjudicator can change the Works Information.