# Can acceptance of a Subcontractor by the Project Manager be withdrawn?

**URL:** <https://reachback.builtintelligence.com/t/can-acceptance-of-a-subcontractor-by-the-project-manager-be-withdrawn/505>\
**Category:** General\
**Created:** [12 October 2012 17:52 UTC](https://reachback.builtintelligence.com/t/can-acceptance-of-a-subcontractor-by-the-project-manager-be-withdrawn/505 "2012-10-12T17:52:37Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 17:52 UTC](https://reachback.builtintelligence.com/t/can-acceptance-of-a-subcontractor-by-the-project-manager-be-withdrawn/505/1 "2012-10-12T17:52:37Z")

</div>

Can acceptance of a Subcontractor by the Project Manager be withdrawn?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 17:52 UTC](https://reachback.builtintelligence.com/t/can-acceptance-of-a-subcontractor-by-the-project-manager-be-withdrawn/505/2 "2012-10-12T17:52:53Z")

</div>

If the appointment of a Subcontractor is in accordance with the Contract, the Project Manager cannot later withdraw acceptance of a Subcontractor.