# Can a contractor have a negative impact upon a global claim?

**URL:** <https://reachback.builtintelligence.com/t/can-a-contractor-have-a-negative-impact-upon-a-global-claim/1574>\
**Category:** Contractor Claims\
**Created:** [18 January 2013 11:04 UTC](https://reachback.builtintelligence.com/t/can-a-contractor-have-a-negative-impact-upon-a-global-claim/1574 "2013-01-18T11:04:46Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 11:04 UTC](https://reachback.builtintelligence.com/t/can-a-contractor-have-a-negative-impact-upon-a-global-claim/1574/1 "2013-01-18T11:04:46Z")

</div>



---

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 11:05 UTC](https://reachback.builtintelligence.com/t/can-a-contractor-have-a-negative-impact-upon-a-global-claim/1574/2 "2013-01-18T11:05:05Z")

</div>

The contractor’s failings and inefficiencies can also bring down a global claim. If it can be shown that these impacted upon the costs claimed then the claim will be deemed inflated and the claim will fail