# At whose risk are Claims, proceedings, compensation and costs payable which are due to use or occupation of the Site by the works or for the purpose of the works which is the unavoidable result of the works?

**URL:** <https://reachback.builtintelligence.com/t/at-whose-risk-are-claims-proceedings-compensation-and-costs-payable-which-are-due-to-use-or-occupation-of-the-site-by-the-works-or-for-the-purpose-of-the-works-which-is-the-unavoidable-result-of-the-works/215>\
**Category:** Risk and Insurance\
**Created:** [10 October 2012 20:01 UTC](https://reachback.builtintelligence.com/t/at-whose-risk-are-claims-proceedings-compensation-and-costs-payable-which-are-due-to-use-or-occupation-of-the-site-by-the-works-or-for-the-purpose-of-the-works-which-is-the-unavoidable-result-of-the-works/215 "2012-10-10T20:01:02Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 20:01 UTC](https://reachback.builtintelligence.com/t/at-whose-risk-are-claims-proceedings-compensation-and-costs-payable-which-are-due-to-use-or-occupation-of-the-site-by-the-works-or-for-the-purpose-of-the-works-which-is-the-unavoidable-result-of-the-works/215/1 "2012-10-10T20:01:02Z")

</div>

At whose risk are Claims, proceedings, compensation and costs payable which are due to use or occupation of the Site by the works or for the purpose of the works which is the unavoidable result of the works?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 20:01 UTC](https://reachback.builtintelligence.com/t/at-whose-risk-are-claims-proceedings-compensation-and-costs-payable-which-are-due-to-use-or-occupation-of-the-site-by-the-works-or-for-the-purpose-of-the-works-which-is-the-unavoidable-result-of-the-works/215/2 "2012-10-10T20:01:29Z")

</div>

The event is at the Employer’s risk (see Clause 80.1).