# As a client, what do I have to do to comply with regulation 9 of CDM 2007?

**URL:** <https://reachback.builtintelligence.com/t/as-a-client-what-do-i-have-to-do-to-comply-with-regulation-9-of-cdm-2007/1307>\
**Category:** CDM\
**Created:** [13 January 2013 09:44 UTC](https://reachback.builtintelligence.com/t/as-a-client-what-do-i-have-to-do-to-comply-with-regulation-9-of-cdm-2007/1307 "2013-01-13T09:44:10Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [13 January 2013 09:44 UTC](https://reachback.builtintelligence.com/t/as-a-client-what-do-i-have-to-do-to-comply-with-regulation-9-of-cdm-2007/1307/1 "2013-01-13T09:44:10Z")

</div>



---

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [24 January 2013 13:45 UTC](https://reachback.builtintelligence.com/t/as-a-client-what-do-i-have-to-do-to-comply-with-regulation-9-of-cdm-2007/1307/2 "2013-01-24T13:45:21Z")

</div>

You need to make sure that:

```
	designers, contractors and other team members that you engage are competent, adequately resourced and appointed early enough for the work they have to do

	you allow sufficient time for each stage of the project, from concept onwards

	you co-operate with others involved with the project to allow other dutyholders to comply with their duties under the Regulations

	you co-ordinate your own work with others involved with the project to ensure the safety of those carrying out the construction work, and others who may be affected by it

	there are suitable management arrangements in place throughout the project to make sure the construction work can be carried out safely and without risk to health – this does not mean managing the work yourself, as it is unlikely that clients have the expertise and resources needed, and it can cause confusion

	your contractors have made arrangements for suitable welfare facilities to be provided from the start and throughout the construction phase

	any fixed workplaces (eg offices, shops, factories, schools) which are to be constructed will comply, in respect of their design and the materials used, with any requirements of the Workplace (Health, Safety and Welfare) Regulations 1992

	relevant information likely to be needed by designers, contractors or others to plan and manage their work is passed to them
```