# Are tests to be done before payment for or marking of Equipment or Plant and Materials?

**URL:** <https://reachback.builtintelligence.com/t/are-tests-to-be-done-before-payment-for-or-marking-of-equipment-or-plant-and-materials/580>\
**Category:** Testing and Defects\
**Created:** [14 October 2012 19:39 UTC](https://reachback.builtintelligence.com/t/are-tests-to-be-done-before-payment-for-or-marking-of-equipment-or-plant-and-materials/580 "2012-10-14T19:39:05Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:39 UTC](https://reachback.builtintelligence.com/t/are-tests-to-be-done-before-payment-for-or-marking-of-equipment-or-plant-and-materials/580/1 "2012-10-14T19:39:05Z")

</div>

Are tests to be done before payment for or marking of Equipment or Plant and Materials?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:39 UTC](https://reachback.builtintelligence.com/t/are-tests-to-be-done-before-payment-for-or-marking-of-equipment-or-plant-and-materials/580/2 "2012-10-14T19:39:20Z")

</div>

Tests are to be done at significant stages including before payment for or marking of Equipment or Plant and Materials (Clause 71.1).