# Are prices adjusted for inflation in Option C: Target Contract with Activity Schedule?

**URL:** <https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-c-target-contract-with-activity-schedule/729>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 15:25 UTC](https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-c-target-contract-with-activity-schedule/729 "2012-10-15T15:25:56Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:25 UTC](https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-c-target-contract-with-activity-schedule/729/1 "2012-10-15T15:25:56Z")

</div>

Are prices adjusted for inflation in Option C: Target Contract with Activity Schedule?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:26 UTC](https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-c-target-contract-with-activity-schedule/729/2 "2012-10-15T15:26:09Z")

</div>

If Option X1: Price adjustment for inflation is used, then prices are adjusted for inflation. This option can only be used with main options A,B,C and D.