# Are prices adjusted for inflation in Option B: Priced Contract with Bill of Quantities?

**URL:** https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-b-priced-contract-with-bill-of-quantities/697
**Category:** NEC3 and NEC4 Contracts
**Created:** [15 October 2012 14:59 UTC](https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-b-priced-contract-with-bill-of-quantities/697 "2012-10-15T14:59:59Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 14:59 UTC](https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-b-priced-contract-with-bill-of-quantities/697/1 "2012-10-15T14:59:59Z")

</div>

Are prices adjusted for inflation in Option B: Priced Contract with Bill of Quantities?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 15:00 UTC](https://reachback.builtintelligence.com/t/are-prices-adjusted-for-inflation-in-option-b-priced-contract-with-bill-of-quantities/697/2 "2012-10-15T15:00:12Z")

</div>

If Option X1: Price adjustment for inflation is used, then prices are adjusted for inflation. This option can only be used with main options A,B,C and D.