# Are payments made in currencies other than the currency of the contract under Option X3?

**URL:** https://reachback.builtintelligence.com/t/are-payments-made-in-currencies-other-than-the-currency-of-the-contract-under-option-x3/874
**Category:** Secondary X, W and Y options
**Created:** [16 October 2012 11:49 UTC](https://reachback.builtintelligence.com/t/are-payments-made-in-currencies-other-than-the-currency-of-the-contract-under-option-x3/874 "2012-10-16T11:49:27Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [16 October 2012 11:49 UTC](https://reachback.builtintelligence.com/t/are-payments-made-in-currencies-other-than-the-currency-of-the-contract-under-option-x3/874/1 "2012-10-16T11:49:27Z")

</div>

Are payments made in currencies other than the currency of the contract under Option X3?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [16 October 2012 11:49 UTC](https://reachback.builtintelligence.com/t/are-payments-made-in-currencies-other-than-the-currency-of-the-contract-under-option-x3/874/2 "2012-10-16T11:49:38Z")

</div>

Yes. The Contractor is paid in currencies other than the currency of the contract under Option X3 (see Clause X3.1).