# After giving a notice of adjudication, how long does a Party have to provide a copy of the information he has provided to the Adjudicator to the other Party?

**URL:** <https://reachback.builtintelligence.com/t/after-giving-a-notice-of-adjudication-how-long-does-a-party-have-to-provide-a-copy-of-the-information-he-has-provided-to-the-adjudicator-to-the-other-party/836>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 18:55 UTC](https://reachback.builtintelligence.com/t/after-giving-a-notice-of-adjudication-how-long-does-a-party-have-to-provide-a-copy-of-the-information-he-has-provided-to-the-adjudicator-to-the-other-party/836 "2012-10-15T18:55:03Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 18:55 UTC](https://reachback.builtintelligence.com/t/after-giving-a-notice-of-adjudication-how-long-does-a-party-have-to-provide-a-copy-of-the-information-he-has-provided-to-the-adjudicator-to-the-other-party/836/1 "2012-10-15T18:55:03Z")

</div>

After giving a notice of adjudication, how long does a Party have to provide a copy of the information and supporting documents he has provided to the Adjudicator to the other Party?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 18:55 UTC](https://reachback.builtintelligence.com/t/after-giving-a-notice-of-adjudication-how-long-does-a-party-have-to-provide-a-copy-of-the-information-he-has-provided-to-the-adjudicator-to-the-other-party/836/2 "2012-10-15T18:55:17Z")

</div>

After giving a notice of adjudication, a Party provides a copy of the information and supporting documents he has provided to the Adjudicator to the other Party within seven days (see Clause W2.3(2)).