# A notification implementing a compensation event should include what?

**URL:** <https://reachback.builtintelligence.com/t/a-notification-implementing-a-compensation-event-should-include-what/723>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 15:21 UTC](https://reachback.builtintelligence.com/t/a-notification-implementing-a-compensation-event-should-include-what/723 "2012-10-15T15:21:42Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:21 UTC](https://reachback.builtintelligence.com/t/a-notification-implementing-a-compensation-event-should-include-what/723/1 "2012-10-15T15:21:42Z")

</div>

A notification implementing a compensation event should include what?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 15:21 UTC](https://reachback.builtintelligence.com/t/a-notification-implementing-a-compensation-event-should-include-what/723/2 "2012-10-15T15:21:54Z")

</div>

The notification implementing a compensation event includes the changes to Key Dates, Prices and the Completion Date (see Clause 65.4).