## [NEC4 contract - accepted programme - changed decision](https://reachback.builtintelligence.com/t/nec4-contract-accepted-programme-changed-decision/22571)

<div class="topic-metadata">

**Author:** [@Ian.Murphy](https://reachback.builtintelligence.com/u/Ian.Murphy)\
**Replies:** 5\
**Last updated:** [22 January 2026 10:55 UTC](https://reachback.builtintelligence.com/t/nec4-contract-accepted-programme-changed-decision/22571 "2026-01-22T10:55:50Z")

</div>

On an NEC4 engineering and construction contract, is the Project Manager permitted to change its decision regarding acceptance of the Contractor’s programme. The situation is that on a circa 6-month long project, 3 mont…

---

## [Under FIDIC, can the Employer require the Contractor to purchase fencing instead of continuing to hire fencing that is already being provided?](https://reachback.builtintelligence.com/t/under-fidic-can-the-employer-require-the-contractor-to-purchase-fencing-instead-of-continuing-to-hire-fencing-that-is-already-being-provided/22561)

<div class="topic-metadata">

**Author:** [@salmo](https://reachback.builtintelligence.com/u/salmo)\
**Replies:** 2\
**Last updated:** [21 January 2026 23:21 UTC](https://reachback.builtintelligence.com/t/under-fidic-can-the-employer-require-the-contractor-to-purchase-fencing-instead-of-continuing-to-hire-fencing-that-is-already-being-provided/22561 "2026-01-21T23:21:50Z")

</div>

Several months ago, the Client/Engineer instructed the Contractor to install Heras panels around a compound, which was not part of the original scope of work. The Contractor purchased the fencing and installed it, and ha…

---

## [Release Notes up to 2026-01-17 Contract Management Sprint 131 132 133](https://reachback.builtintelligence.com/t/release-notes-up-to-2026-01-17-contract-management-sprint-131-132-133/22576)

<div class="topic-metadata">

**Author:** [@liz\_exley](https://reachback.builtintelligence.com/u/liz_exley)\
**Replies:** 0\
**Last updated:** [20 January 2026 17:00 UTC](https://reachback.builtintelligence.com/t/release-notes-up-to-2026-01-17-contract-management-sprint-131-132-133/22576 "2026-01-20T17:00:38Z")

</div>

This release contains improvements and bug fixes. \*New and Improved \*Improvements Allow Admins to add/update/remove comments on the contract user table (eg explaining reason for access). These can also be viewed on the…

---

## [EOT under X22 - Stage 1 Impacts to Stage 2 Prior to NTP](https://reachback.builtintelligence.com/t/eot-under-x22-stage-1-impacts-to-stage-2-prior-to-ntp/22575)

<div class="topic-metadata">

**Author:** [@ZAW](https://reachback.builtintelligence.com/u/ZAW)\
**Replies:** 0\
**Last updated:** [20 January 2026 16:19 UTC](https://reachback.builtintelligence.com/t/eot-under-x22-stage-1-impacts-to-stage-2-prior-to-ntp/22575 "2026-01-20T16:19:03Z")

</div>

Hello, I am hoping someone might be able to give some clarity; on a contract with X22, where a valid CE for time occurs in stage 1, would this be factored into the dates for stage 2 or would this only be applicable as pa…

---

## [NEC4 Option A Term Service - Fee Percentage](https://reachback.builtintelligence.com/t/nec4-option-a-term-service-fee-percentage/22512)

<div class="topic-metadata">

**Author:** [@trauts80](https://reachback.builtintelligence.com/u/trauts80)\
**Replies:** 2\
**Last updated:** [16 January 2026 14:19 UTC](https://reachback.builtintelligence.com/t/nec4-option-a-term-service-fee-percentage/22512 "2026-01-16T14:19:17Z")

</div>

We have a received a Compensation Event from a Contractor under an NEC4 Term Service contract. The quotation is made up of people costs and crane hire. The fee percentage has been correctly applied to the whole of the qu…

---

## [Design Liability](https://reachback.builtintelligence.com/t/design-liability/22403)

<div class="topic-metadata">

**Author:** [@turleya](https://reachback.builtintelligence.com/u/turleya)\
**Replies:** 2\
**Last updated:** [16 January 2026 13:44 UTC](https://reachback.builtintelligence.com/t/design-liability/22403 "2026-01-16T13:44:08Z")

</div>

In a NEC3 Option A design and build contract, who is liable for the cost of correcting a design error after it is built?

---

## [NEC4 Option C Sectional Completions and Scope removal](https://reachback.builtintelligence.com/t/nec4-option-c-sectional-completions-and-scope-removal/22574)

<div class="topic-metadata">

**Author:** [@C1TPT](https://reachback.builtintelligence.com/u/C1TPT)\
**Replies:** 2\
**Last updated:** [15 January 2026 18:29 UTC](https://reachback.builtintelligence.com/t/nec4-option-c-sectional-completions-and-scope-removal/22574 "2026-01-15T18:29:12Z")

</div>

Hi All, I have a question about what happens to sectional completion dates when scope is removed from a project. I’m starting a project that has 9 phases, each having their own sectional completion dates at the end. Eac…

---

## [NEC4 Option B CE Reduces total quantity](https://reachback.builtintelligence.com/t/nec4-option-b-ce-reduces-total-quantity/22530)

<div class="topic-metadata">

**Author:** [@jdd89](https://reachback.builtintelligence.com/u/jdd89)\
**Replies:** 2\
**Last updated:** [15 January 2026 17:09 UTC](https://reachback.builtintelligence.com/t/nec4-option-b-ce-reduces-total-quantity/22530 "2026-01-15T17:09:39Z")

</div>

The Client has issued a PMI with revised drawings which reduces the quantities in the BoQ and in some cases completely omits BoQ items. No work has been undertaken on these BoQ items. Under Clause 63.1, where the quanti…

---

## [NEC 4 option A SSCC people costs](https://reachback.builtintelligence.com/t/nec-4-option-a-sscc-people-costs/22431)

<div class="topic-metadata">

**Author:** [@EmmaQS](https://reachback.builtintelligence.com/u/EmmaQS)\
**Replies:** 2\
**Last updated:** [15 January 2026 16:55 UTC](https://reachback.builtintelligence.com/t/nec-4-option-a-sscc-people-costs/22431 "2026-01-15T16:55:57Z")

</div>

Is the contractor entitled to recovery of pricing the CE under the people costs of the SSCC. So are they entitled to QS time and planner time to assess cost and programme implication of the event?

---

## [Assessing Time Impact CEs out of chronological order](https://reachback.builtintelligence.com/t/assessing-time-impact-ces-out-of-chronological-order/22418)

<div class="topic-metadata">

**Author:** [@LAP](https://reachback.builtintelligence.com/u/LAP)\
**Replies:** 2\
**Last updated:** [15 January 2026 14:38 UTC](https://reachback.builtintelligence.com/t/assessing-time-impact-ces-out-of-chronological-order/22418 "2026-01-15T14:38:17Z")

</div>

All, I currently work on a large infrastructure job and the amount of CEs is huge (some being larger than others). As a result to continue to progress the change account, the Change Manager and the team have agreed to a…

---

## [Articles of Agreement - purpose and uses instead of or together with JCT](https://reachback.builtintelligence.com/t/articles-of-agreement-purpose-and-uses-instead-of-or-together-with-jct/22488)

<div class="topic-metadata">

**Author:** [@SNIKO](https://reachback.builtintelligence.com/u/SNIKO)\
**Replies:** 2\
**Last updated:** [14 January 2026 13:26 UTC](https://reachback.builtintelligence.com/t/articles-of-agreement-purpose-and-uses-instead-of-or-together-with-jct/22488 "2026-01-14T13:26:08Z")

</div>

Can the JCT form of agreement be replaced with a cover contract/articles of agreement incorporating it by reference only? If affirmative, what are the pros and cons of using this approach? It seems to me that it will be …

---

## [Possible Defect After the Defects Certificate](https://reachback.builtintelligence.com/t/possible-defect-after-the-defects-certificate/22411)

<div class="topic-metadata">

**Author:** [@MJR](https://reachback.builtintelligence.com/u/MJR)\
**Replies:** 1\
**Last updated:** [14 January 2026 12:04 UTC](https://reachback.builtintelligence.com/t/possible-defect-after-the-defects-certificate/22411 "2026-01-14T12:04:41Z")

</div>

Contractor completed an NEC3 ECC Option A (no design responsibility) scheme a number of years ago (completion 2020, defects certificate received 2021). The Employer has recently contacted the Contractor and stated that g…

---

## [Work schedules JCT Minor Works](https://reachback.builtintelligence.com/t/work-schedules-jct-minor-works/22442)

<div class="topic-metadata">

**Author:** [@jim823408](https://reachback.builtintelligence.com/u/jim823408)\
**Replies:** 1\
**Last updated:** [14 January 2026 11:54 UTC](https://reachback.builtintelligence.com/t/work-schedules-jct-minor-works/22442 "2026-01-14T11:54:23Z")

</div>

Given that the JCT 2024 Minor Works contract is based upon a lump sum, who takes the risk if the quantities or descriptions stated in the Work Schedules are incorrect (e.g. a different quantity in the Work Schedules than…

---

## [JCT SBC subcontract - omission of works](https://reachback.builtintelligence.com/t/jct-sbc-subcontract-omission-of-works/22446)

<div class="topic-metadata">

**Author:** [@EmmaQS](https://reachback.builtintelligence.com/u/EmmaQS)\
**Replies:** 1\
**Last updated:** [14 January 2026 11:53 UTC](https://reachback.builtintelligence.com/t/jct-sbc-subcontract-omission-of-works/22446 "2026-01-14T11:53:51Z")

</div>

We are working on a site where the client has omitted a full package of work and is undertaking the work himself using a slightly different system. This has been omitted from our scope. We have placed an order with a sub…

---

## [General notice 2:15](https://reachback.builtintelligence.com/t/general-notice-2-15/22492)

<div class="topic-metadata">

**Author:** [@joseph.avazian](https://reachback.builtintelligence.com/u/joseph.avazian)\
**Replies:** 1\
**Last updated:** [14 January 2026 11:49 UTC](https://reachback.builtintelligence.com/t/general-notice-2-15/22492 "2026-01-14T11:49:37Z")

</div>

"In General notice 2:15, what are the implications for the contractor if no notice is given of a divergence of statutory requirements.

---

## [Management Costs on Changes, Loss & Expense, JCT Design and Build](https://reachback.builtintelligence.com/t/management-costs-on-changes-loss-expense-jct-design-and-build/22506)

<div class="topic-metadata">

**Author:** [@sandramullins74](https://reachback.builtintelligence.com/u/sandramullins74)\
**Replies:** 1\
**Last updated:** [14 January 2026 11:33 UTC](https://reachback.builtintelligence.com/t/management-costs-on-changes-loss-expense-jct-design-and-build/22506 "2026-01-14T11:33:40Z")

</div>

Under a JCT DB can a contractor include within their variations costs for ‘people involved with the change’ for example, additional time for Operations Director, Surveyor to prepare the variation and then also claim for…

---

## [Application of X1.4 if Contractor is past Completion Date](https://reachback.builtintelligence.com/t/application-of-x1-4-if-contractor-is-past-completion-date/22568)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 1\
**Last updated:** [5 January 2026 16:21 UTC](https://reachback.builtintelligence.com/t/application-of-x1-4-if-contractor-is-past-completion-date/22568 "2026-01-05T16:21:06Z")

</div>

NEC4 Option C. We have a Contractor that is now in delay and is completing their works past the Contract’s Completion Date. Should we still be applying an X1.4 increase to the total of prices after each PM assessment o…

---

## [Authority imposing conditions](https://reachback.builtintelligence.com/t/authority-imposing-conditions/22429)

<div class="topic-metadata">

**Author:** [@InfraPM](https://reachback.builtintelligence.com/u/InfraPM)\
**Replies:** 1\
**Last updated:** [2 January 2026 11:00 UTC](https://reachback.builtintelligence.com/t/authority-imposing-conditions/22429 "2026-01-02T11:00:49Z")

</div>

We are managing an NEC3 construction contract and the local authority are imposing conditions that restrict how the works must be delivered eg, working hours, noise levels etc. The works information contains general requ…

---

## [NEC4 ECC Change to Critical Path](https://reachback.builtintelligence.com/t/nec4-ecc-change-to-critical-path/22536)

<div class="topic-metadata">

**Author:** [@David](https://reachback.builtintelligence.com/u/David)\
**Replies:** 1\
**Last updated:** [2 January 2026 10:56 UTC](https://reachback.builtintelligence.com/t/nec4-ecc-change-to-critical-path/22536 "2026-01-02T10:56:39Z")

</div>

NEC4 ECC Option A contract. 6 months into 24 month contract. Contractor has submitted a CE for 12 week delay and significant delay costs due to a utility provider taking longer than agreed to complete works. All programm…

---

## [Costs of Producing a Quotation during a delay period](https://reachback.builtintelligence.com/t/costs-of-producing-a-quotation-during-a-delay-period/22538)

<div class="topic-metadata">

**Author:** [@paulob](https://reachback.builtintelligence.com/u/paulob)\
**Replies:** 1\
**Last updated:** [2 January 2026 10:50 UTC](https://reachback.builtintelligence.com/t/costs-of-producing-a-quotation-during-a-delay-period/22538 "2026-01-02T10:50:47Z")

</div>

On a subcontract where the subcontractor is beyond his completion date and planned completion date can it recover the costs for preparing quotations for additional CEs given that prelims are not being recovered elsewhere…

---

## [NEC4 Option A 'fee percentage'](https://reachback.builtintelligence.com/t/nec4-option-a-fee-percentage/22510)

<div class="topic-metadata">

**Author:** [@jon.milner](https://reachback.builtintelligence.com/u/jon.milner)\
**Replies:** 1\
**Last updated:** [2 January 2026 10:46 UTC](https://reachback.builtintelligence.com/t/nec4-option-a-fee-percentage/22510 "2026-01-02T10:46:00Z")

</div>

We buy in material from a sister company and use subcontract labour. When pricing an Option A we bundle these costs and hike up to give us a buffer on a project Lets say 30% margin. Our Commercial team do not want me …

---

## [Disallow costs for LADs non applied](https://reachback.builtintelligence.com/t/disallow-costs-for-lads-non-applied/22564)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 3\
**Last updated:** [2 January 2026 10:37 UTC](https://reachback.builtintelligence.com/t/disallow-costs-for-lads-non-applied/22564 "2026-01-02T10:37:23Z")

</div>

NEC4 Option C clause 11.2(26) states that a disallowed cost is a cost which should not have been paid to a Subcontractor or supplier in accordance with its contract. If a contractor should have levied LADs against a sub…

---

## [Subcontract documents not submitted by Contractor](https://reachback.builtintelligence.com/t/subcontract-documents-not-submitted-by-contractor/22408)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 3\
**Last updated:** [2 January 2026 09:23 UTC](https://reachback.builtintelligence.com/t/subcontract-documents-not-submitted-by-contractor/22408 "2026-01-02T09:23:46Z")

</div>

NEC4 Option C. What happens if a Contractor simply does not submit the Subcontract documents for PM acceptance in-line with the contract, but continues to use them without PM acceptance having been achieved?

---

## [What to show on impacted programme?](https://reachback.builtintelligence.com/t/what-to-show-on-impacted-programme/22560)

<div class="topic-metadata">

**Author:** [@Anonn](https://reachback.builtintelligence.com/u/Anonn)\
**Replies:** 1\
**Last updated:** [2 January 2026 09:09 UTC](https://reachback.builtintelligence.com/t/what-to-show-on-impacted-programme/22560 "2026-01-02T09:09:27Z")

</div>

I understand the principles of submitting a programme for acceptance, in terms of the completion date can’t move unless there is an implemented CE, demonstrating a change to planned completion. However, when submitting …

---

## [NEC forecasting unknown pricing](https://reachback.builtintelligence.com/t/nec-forecasting-unknown-pricing/22562)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 1\
**Last updated:** [2 January 2026 08:59 UTC](https://reachback.builtintelligence.com/t/nec-forecasting-unknown-pricing/22562 "2026-01-02T08:59:25Z")

</div>

The Project Manager instructed the Contractor to undertake construction work in the belief that the designs for this work (previously instructed many months before) would be sufficiently developed to allow adequate prici…

---

## [2025: The Year in Review](https://reachback.builtintelligence.com/t/2025-the-year-in-review/22567)

<div class="topic-metadata">

**Author:** [@system](https://reachback.builtintelligence.com/u/system)\
**Replies:** 0\
**Last updated:** [1 January 2026 17:09 UTC](https://reachback.builtintelligence.com/t/2025-the-year-in-review/22567 "2026-01-01T17:09:56Z")

</div>

2025's Top Users Most Time Reading User Hours Read @Andrew\_W-I 8 @Andy.ATNEC 5 @dave\_bates 4 @Peter\_Papadakis 3 @engineering 3 @jpgarvin 3 @juanaugusto85 2 @JMR 2 @SladeW 2 @MylesScr…

---

## [The use of AI to support scope writing](https://reachback.builtintelligence.com/t/the-use-of-ai-to-support-scope-writing/22566)

<div class="topic-metadata">

**Author:** [@p\_coates90](https://reachback.builtintelligence.com/u/p_coates90)\
**Replies:** 0\
**Last updated:** [26 December 2025 11:57 UTC](https://reachback.builtintelligence.com/t/the-use-of-ai-to-support-scope-writing/22566 "2025-12-26T11:57:46Z")

</div>

ok, before you all start throwing stones at me, has anyone started to use AI to support with the drafting of Scope or Works Informations, I have had a play at asking co-pilot to review a document for consistency with the…

---

## [NEC4 Optional Clause X1](https://reachback.builtintelligence.com/t/nec4-optional-clause-x1/22559)

<div class="topic-metadata">

**Author:** [@Robert\_Trembath](https://reachback.builtintelligence.com/u/Robert_Trembath)\
**Replies:** 1\
**Last updated:** [22 December 2025 11:30 UTC](https://reachback.builtintelligence.com/t/nec4-optional-clause-x1/22559 "2025-12-22T11:30:18Z")

</div>

Currently managing an NEC4 Option A with Clause X1 selected. The indicies used is the BCIS TPI. This is often updated retrospectively, so an individual index can change from being forecast to provisional to final over t…

---

## [Ambiguity or Inconsistency](https://reachback.builtintelligence.com/t/ambiguity-or-inconsistency/22558)

<div class="topic-metadata">

**Author:** [@WKYIP](https://reachback.builtintelligence.com/u/WKYIP)\
**Replies:** 4\
**Last updated:** [12 December 2025 12:17 UTC](https://reachback.builtintelligence.com/t/ambiguity-or-inconsistency/22558 "2025-12-12T12:17:34Z")

</div>

I am currently working on a contract using NEC4 Contracts According to the Particular Specification, material for water pipe should be A or B (A is more expensive than B). The Project Manager subsequently confirmed that…

---

## [Programme impact to be shown on CE quotations](https://reachback.builtintelligence.com/t/programme-impact-to-be-shown-on-ce-quotations/22557)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 3\
**Last updated:** [10 December 2025 14:18 UTC](https://reachback.builtintelligence.com/t/programme-impact-to-be-shown-on-ce-quotations/22557 "2025-12-10T14:18:57Z")

</div>

Whilst I am clear that Contractor’s CE quotations should show impact of CE on Key Dates and Completion Date, should every CE quotation show general impact on programme and movement of other activities, even if those prog…