## [Supply Contract - TQs covered in a previous CE](https://reachback.builtintelligence.com/t/supply-contract-tqs-covered-in-a-previous-ce/22686)

<div class="topic-metadata">

**Author:** [@johnahoughton](https://reachback.builtintelligence.com/u/johnahoughton)\
**Replies:** 0\
**Last updated:** [17 November 2026 17:41 UTC](https://reachback.builtintelligence.com/t/supply-contract-tqs-covered-in-a-previous-ce/22686 "2026-11-17T17:41:34Z")

</div>

Supplier recovered costs for resolving TQs under a CE. The CE was implemented on CEMAR. 2 years later they are seeking to add costs. They have raised a new CE which we somehow accepted and they are looking to recover co…

---

## [Carbon border adjustment mechanism (CBAM)](https://reachback.builtintelligence.com/t/carbon-border-adjustment-mechanism-cbam/22676)

<div class="topic-metadata">

**Author:** [@Hughesde](https://reachback.builtintelligence.com/u/Hughesde)\
**Replies:** 2\
**Last updated:** [28 October 2026 15:44 UTC](https://reachback.builtintelligence.com/t/carbon-border-adjustment-mechanism-cbam/22676 "2026-10-28T15:44:59Z")

</div>

My understanding is that UK CBAM starts on 1 January 2027. It places a carbon-related tax on specified imported goods. The introduction of this levy is a result of lesilation and therefore presumably will be covered by …

---

## [EOT entitlement for delay post handover](https://reachback.builtintelligence.com/t/eot-entitlement-for-delay-post-handover/22631)

<div class="topic-metadata">

**Author:** [@EmmaQS](https://reachback.builtintelligence.com/u/EmmaQS)\
**Replies:** 3\
**Last updated:** [13 August 2026 11:14 UTC](https://reachback.builtintelligence.com/t/eot-entitlement-for-delay-post-handover/22631 "2026-08-13T11:14:00Z")

</div>

We have a situation were we are due to handover the project without stats in place which are clients risk. The Works will be complete mid September, it is then looking like we will keep possession of the site for a furth…

---

## [Restricted Working/Access Compensation Event Entitlement](https://reachback.builtintelligence.com/t/restricted-working-access-compensation-event-entitlement/22646)

<div class="topic-metadata">

**Author:** [@ZAW](https://reachback.builtintelligence.com/u/ZAW)\
**Replies:** 3\
**Last updated:** [3 July 2026 10:45 UTC](https://reachback.builtintelligence.com/t/restricted-working-access-compensation-event-entitlement/22646 "2026-07-03T10:45:12Z")

</div>

Working under an NEC4 Option E contract; we have had a situation where a small part of the site has been taken over by a third party for works, and subsequently handed back. During this time, access to that part of the s…

---

## [Delay to Power On NEC4](https://reachback.builtintelligence.com/t/delay-to-power-on-nec4/22622)

<div class="topic-metadata">

**Author:** [@EmmaQS](https://reachback.builtintelligence.com/u/EmmaQS)\
**Replies:** 3\
**Last updated:** [20 April 2026 12:55 UTC](https://reachback.builtintelligence.com/t/delay-to-power-on-nec4/22622 "2026-04-20T12:55:05Z")

</div>

Hi All, I think this is a common problem with regards to statutory authorities and any advice would be appreciated. The client was supposed to provide power to site months ago, this was a provisional sum that was omitt…

---

## [Effects on fuel prices due to the USA/Iran War](https://reachback.builtintelligence.com/t/effects-on-fuel-prices-due-to-the-usa-iran-war/22616)

<div class="topic-metadata">

**Author:** [@Hughesde](https://reachback.builtintelligence.com/u/Hughesde)\
**Replies:** 1\
**Last updated:** [13 April 2026 09:18 UTC](https://reachback.builtintelligence.com/t/effects-on-fuel-prices-due-to-the-usa-iran-war/22616 "2026-04-13T09:18:49Z")

</div>

We are operating a NEC 4 Term Service contract for roads maintenance. The Contractor has submitted an early warning regarding the exceptional increases in fuel prices due to the UAS/Iran war. We sympathetic to the Cont…

---

## [Subcontracted costs in a NEC4 Option E CE](https://reachback.builtintelligence.com/t/subcontracted-costs-in-a-nec4-option-e-ce/22606)

<div class="topic-metadata">

**Author:** [@Som2310](https://reachback.builtintelligence.com/u/Som2310)\
**Replies:** 1\
**Last updated:** [26 March 2026 14:27 UTC](https://reachback.builtintelligence.com/t/subcontracted-costs-in-a-nec4-option-e-ce/22606 "2026-03-26T14:27:30Z")

</div>

Hi all, I am working from the client side on a project where we have a contractor carrying out works under the NEC4 Option E form of contract. A CE arose, the contractor priced this and we accepted it. Within the the q…

---

## [NEC3 Option E - Costs for correcting defects and resulting delay](https://reachback.builtintelligence.com/t/nec3-option-e-costs-for-correcting-defects-and-resulting-delay/22573)

<div class="topic-metadata">

**Author:** [@paul.cavanagh2](https://reachback.builtintelligence.com/u/paul.cavanagh2)\
**Replies:** 3\
**Last updated:** [11 February 2026 15:34 UTC](https://reachback.builtintelligence.com/t/nec3-option-e-costs-for-correcting-defects-and-resulting-delay/22573 "2026-02-11T15:34:43Z")

</div>

Hi. I’m looking for some guidance on a current issue. We (Employer) are engaged on an Option E contact, part of which is for the Contractor to carry out ground investigation works. There has been a failure of some plant …

---

## [NEC3: Recover Staff Costs During Christmas Shutdown?](https://reachback.builtintelligence.com/t/nec3-recover-staff-costs-during-christmas-shutdown/22539)

<div class="topic-metadata">

**Author:** [@jjakala](https://reachback.builtintelligence.com/u/jjakala)\
**Replies:** 6\
**Last updated:** [23 January 2026 09:06 UTC](https://reachback.builtintelligence.com/t/nec3-recover-staff-costs-during-christmas-shutdown/22539 "2026-01-23T09:06:52Z")

</div>

Hi All, We are a Subcontractor working under an NEC3 contract and following a recent instruction changing access dates, our original planned Completion has now moved into the New Year. A revised programme was prepared …

---

## [NEC4 contract - accepted programme - changed decision](https://reachback.builtintelligence.com/t/nec4-contract-accepted-programme-changed-decision/22571)

<div class="topic-metadata">

**Author:** [@Ian.Murphy](https://reachback.builtintelligence.com/u/Ian.Murphy)\
**Replies:** 5\
**Last updated:** [22 January 2026 10:55 UTC](https://reachback.builtintelligence.com/t/nec4-contract-accepted-programme-changed-decision/22571 "2026-01-22T10:55:50Z")

</div>

On an NEC4 engineering and construction contract, is the Project Manager permitted to change its decision regarding acceptance of the Contractor’s programme. The situation is that on a circa 6-month long project, 3 mont…

---

## [EOT under X22 - Stage 1 Impacts to Stage 2 Prior to NTP](https://reachback.builtintelligence.com/t/eot-under-x22-stage-1-impacts-to-stage-2-prior-to-ntp/22575)

<div class="topic-metadata">

**Author:** [@ZAW](https://reachback.builtintelligence.com/u/ZAW)\
**Replies:** 0\
**Last updated:** [20 January 2026 16:19 UTC](https://reachback.builtintelligence.com/t/eot-under-x22-stage-1-impacts-to-stage-2-prior-to-ntp/22575 "2026-01-20T16:19:03Z")

</div>

Hello, I am hoping someone might be able to give some clarity; on a contract with X22, where a valid CE for time occurs in stage 1, would this be factored into the dates for stage 2 or would this only be applicable as pa…

---

## [NEC4 Option B CE Reduces total quantity](https://reachback.builtintelligence.com/t/nec4-option-b-ce-reduces-total-quantity/22530)

<div class="topic-metadata">

**Author:** [@jdd89](https://reachback.builtintelligence.com/u/jdd89)\
**Replies:** 2\
**Last updated:** [15 January 2026 17:09 UTC](https://reachback.builtintelligence.com/t/nec4-option-b-ce-reduces-total-quantity/22530 "2026-01-15T17:09:39Z")

</div>

The Client has issued a PMI with revised drawings which reduces the quantities in the BoQ and in some cases completely omits BoQ items. No work has been undertaken on these BoQ items. Under Clause 63.1, where the quanti…

---

## [NEC 4 option A SSCC people costs](https://reachback.builtintelligence.com/t/nec-4-option-a-sscc-people-costs/22431)

<div class="topic-metadata">

**Author:** [@EmmaQS](https://reachback.builtintelligence.com/u/EmmaQS)\
**Replies:** 2\
**Last updated:** [15 January 2026 16:55 UTC](https://reachback.builtintelligence.com/t/nec-4-option-a-sscc-people-costs/22431 "2026-01-15T16:55:57Z")

</div>

Is the contractor entitled to recovery of pricing the CE under the people costs of the SSCC. So are they entitled to QS time and planner time to assess cost and programme implication of the event?

---

## [Assessing Time Impact CEs out of chronological order](https://reachback.builtintelligence.com/t/assessing-time-impact-ces-out-of-chronological-order/22418)

<div class="topic-metadata">

**Author:** [@LAP](https://reachback.builtintelligence.com/u/LAP)\
**Replies:** 2\
**Last updated:** [15 January 2026 14:38 UTC](https://reachback.builtintelligence.com/t/assessing-time-impact-ces-out-of-chronological-order/22418 "2026-01-15T14:38:17Z")

</div>

All, I currently work on a large infrastructure job and the amount of CEs is huge (some being larger than others). As a result to continue to progress the change account, the Change Manager and the team have agreed to a…

---

## [Application of X1.4 if Contractor is past Completion Date](https://reachback.builtintelligence.com/t/application-of-x1-4-if-contractor-is-past-completion-date/22568)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 1\
**Last updated:** [5 January 2026 16:21 UTC](https://reachback.builtintelligence.com/t/application-of-x1-4-if-contractor-is-past-completion-date/22568 "2026-01-05T16:21:06Z")

</div>

NEC4 Option C. We have a Contractor that is now in delay and is completing their works past the Contract’s Completion Date. Should we still be applying an X1.4 increase to the total of prices after each PM assessment o…

---

## [Authority imposing conditions](https://reachback.builtintelligence.com/t/authority-imposing-conditions/22429)

<div class="topic-metadata">

**Author:** [@InfraPM](https://reachback.builtintelligence.com/u/InfraPM)\
**Replies:** 1\
**Last updated:** [2 January 2026 11:00 UTC](https://reachback.builtintelligence.com/t/authority-imposing-conditions/22429 "2026-01-02T11:00:49Z")

</div>

We are managing an NEC3 construction contract and the local authority are imposing conditions that restrict how the works must be delivered eg, working hours, noise levels etc. The works information contains general requ…

---

## [NEC4 ECC Change to Critical Path](https://reachback.builtintelligence.com/t/nec4-ecc-change-to-critical-path/22536)

<div class="topic-metadata">

**Author:** [@David](https://reachback.builtintelligence.com/u/David)\
**Replies:** 1\
**Last updated:** [2 January 2026 10:56 UTC](https://reachback.builtintelligence.com/t/nec4-ecc-change-to-critical-path/22536 "2026-01-02T10:56:39Z")

</div>

NEC4 ECC Option A contract. 6 months into 24 month contract. Contractor has submitted a CE for 12 week delay and significant delay costs due to a utility provider taking longer than agreed to complete works. All programm…

---

## [Costs of Producing a Quotation during a delay period](https://reachback.builtintelligence.com/t/costs-of-producing-a-quotation-during-a-delay-period/22538)

<div class="topic-metadata">

**Author:** [@paulob](https://reachback.builtintelligence.com/u/paulob)\
**Replies:** 1\
**Last updated:** [2 January 2026 10:50 UTC](https://reachback.builtintelligence.com/t/costs-of-producing-a-quotation-during-a-delay-period/22538 "2026-01-02T10:50:47Z")

</div>

On a subcontract where the subcontractor is beyond his completion date and planned completion date can it recover the costs for preparing quotations for additional CEs given that prelims are not being recovered elsewhere…

---

## [Disallow costs for LADs non applied](https://reachback.builtintelligence.com/t/disallow-costs-for-lads-non-applied/22564)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 3\
**Last updated:** [2 January 2026 10:37 UTC](https://reachback.builtintelligence.com/t/disallow-costs-for-lads-non-applied/22564 "2026-01-02T10:37:23Z")

</div>

NEC4 Option C clause 11.2(26) states that a disallowed cost is a cost which should not have been paid to a Subcontractor or supplier in accordance with its contract. If a contractor should have levied LADs against a sub…

---

## [NEC forecasting unknown pricing](https://reachback.builtintelligence.com/t/nec-forecasting-unknown-pricing/22562)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 1\
**Last updated:** [2 January 2026 08:59 UTC](https://reachback.builtintelligence.com/t/nec-forecasting-unknown-pricing/22562 "2026-01-02T08:59:25Z")

</div>

The Project Manager instructed the Contractor to undertake construction work in the belief that the designs for this work (previously instructed many months before) would be sufficiently developed to allow adequate prici…

---

## [The use of AI to support scope writing](https://reachback.builtintelligence.com/t/the-use-of-ai-to-support-scope-writing/22566)

<div class="topic-metadata">

**Author:** [@p\_coates90](https://reachback.builtintelligence.com/u/p_coates90)\
**Replies:** 0\
**Last updated:** [26 December 2025 11:57 UTC](https://reachback.builtintelligence.com/t/the-use-of-ai-to-support-scope-writing/22566 "2025-12-26T11:57:46Z")

</div>

ok, before you all start throwing stones at me, has anyone started to use AI to support with the drafting of Scope or Works Informations, I have had a play at asking co-pilot to review a document for consistency with the…

---

## [Programme impact to be shown on CE quotations](https://reachback.builtintelligence.com/t/programme-impact-to-be-shown-on-ce-quotations/22557)

<div class="topic-metadata">

**Author:** [@SaintNEC](https://reachback.builtintelligence.com/u/SaintNEC)\
**Replies:** 3\
**Last updated:** [10 December 2025 14:18 UTC](https://reachback.builtintelligence.com/t/programme-impact-to-be-shown-on-ce-quotations/22557 "2025-12-10T14:18:57Z")

</div>

Whilst I am clear that Contractor’s CE quotations should show impact of CE on Key Dates and Completion Date, should every CE quotation show general impact on programme and movement of other activities, even if those prog…

---

## [NEC 3/NEC4 Option B & D - Remeasure of staff/prelims in a BoQ](https://reachback.builtintelligence.com/t/nec-3-nec4-option-b-d-remeasure-of-staff-prelims-in-a-boq/22486)

<div class="topic-metadata">

**Author:** [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Replies:** 1\
**Last updated:** [12 September 2025 09:34 UTC](https://reachback.builtintelligence.com/t/nec-3-nec4-option-b-d-remeasure-of-staff-prelims-in-a-boq/22486 "2025-09-12T09:34:33Z")

</div>

Hello - This question follows on from a recent post on the forum. When using a unamended NEC 3/NEC4 Option B, or D contract, are the staff rates open to remeasurement ? For example if the BoQ listed the following: Item:…

---

## [NEC Option A - Quotation cost](https://reachback.builtintelligence.com/t/nec-option-a-quotation-cost/22468)

<div class="topic-metadata">

**Author:** [@EmmaQS](https://reachback.builtintelligence.com/u/EmmaQS)\
**Replies:** 6\
**Last updated:** [29 August 2025 14:52 UTC](https://reachback.builtintelligence.com/t/nec-option-a-quotation-cost/22468 "2025-08-29T14:52:54Z")

</div>

Is the contractor entitled to recover the cost of QS and programmer time used when pricings CEs

---

## [Rejecting a programme as it's impractical](https://reachback.builtintelligence.com/t/rejecting-a-programme-as-its-impractical/22475)

<div class="topic-metadata">

**Author:** [@csb1](https://reachback.builtintelligence.com/u/csb1)\
**Replies:** 2\
**Last updated:** [29 August 2025 13:41 UTC](https://reachback.builtintelligence.com/t/rejecting-a-programme-as-its-impractical/22475 "2025-08-29T13:41:22Z")

</div>

Can I reject a subcontractors revised programme as it’s impractical under clause 31.3? As main contractor we coordinated our works with their initial progrogamme and have now set up temporary works that is very expensiv…

---

## [NEC Option A Risk Register Exclusions](https://reachback.builtintelligence.com/t/nec-option-a-risk-register-exclusions/22459)

<div class="topic-metadata">

**Author:** [@kgormley](https://reachback.builtintelligence.com/u/kgormley)\
**Replies:** 1\
**Last updated:** [15 August 2025 10:13 UTC](https://reachback.builtintelligence.com/t/nec-option-a-risk-register-exclusions/22459 "2025-08-15T10:13:40Z")

</div>

Currently working under an NEC 3 Option A Term Service Agreement in which the Risk Register states that the cost of road sweeper is excluded from the contractor’s costs and a contingency sum is allowed in the risk pot. …

---

## [NEC - Consequential Loss](https://reachback.builtintelligence.com/t/nec-consequential-loss/22353)

<div class="topic-metadata">

**Author:** [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Replies:** 5\
**Last updated:** [10 July 2025 15:58 UTC](https://reachback.builtintelligence.com/t/nec-consequential-loss/22353 "2025-07-10T15:58:34Z")

</div>

There are several routes under NEC for the Employer/Client to pursue the Contractor for consequential loss. One being Cl25.3 (missing a Key Date), others being late payments (interest) etc. In an unamended contract does …

---

## [NEC3 Non payment by the Employer - Compensation Event with Y(UK)2](https://reachback.builtintelligence.com/t/nec3-non-payment-by-the-employer-compensation-event-with-y-uk-2/22400)

<div class="topic-metadata">

**Author:** [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Replies:** 2\
**Last updated:** [10 July 2025 12:08 UTC](https://reachback.builtintelligence.com/t/nec3-non-payment-by-the-employer-compensation-event-with-y-uk-2/22400 "2025-07-10T12:08:51Z")

</div>

The NEC Guidance notes state that when using Y(UK)2 the following apply: From Payment Assessment Date the PM has 7 days to issue the Payment Certificate, becoming the “due date for payment” From the “due date for payme…

---

## [NEC4 Option C - X1 adjustments to the target](https://reachback.builtintelligence.com/t/nec4-option-c-x1-adjustments-to-the-target/22382)

<div class="topic-metadata">

**Author:** [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Replies:** 2\
**Last updated:** [4 July 2025 11:00 UTC](https://reachback.builtintelligence.com/t/nec4-option-c-x1-adjustments-to-the-target/22382 "2025-07-04T11:00:58Z")

</div>

Under an unamended Option C (NEC4) with X1 included. Please confirm the following is correct: The PAF is determined at each payment application (say 4 weekly, using: L-B/B), the adjustment is not applied to the payment …

---

## [NEC 4 Option A - ECI?](https://reachback.builtintelligence.com/t/nec-4-option-a-eci/22348)

<div class="topic-metadata">

**Author:** [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Replies:** 2\
**Last updated:** [22 June 2025 16:41 UTC](https://reachback.builtintelligence.com/t/nec-4-option-a-eci/22348 "2025-06-22T16:41:35Z")

</div>

We are tendering a project where the ITT refers to the main contract being awarded as an NEC 4 Option A. In addition, the ITT then mentions the option of an ECI for the successful tenderer. NEC4 only includes X22 in Opti…