NEC4 Option B - CE assessment
|
|
1
|
1652
|
25 November 2021
|
Project Managers Assumptions (after quote has been submitted)
|
|
2
|
647
|
23 November 2021
|
NEC4 Option B - Works of similar character - BoQ Rates or Defined Cost
|
|
2
|
728
|
17 November 2021
|
Introduction of new Key Dates mid contract
|
|
1
|
414
|
17 November 2021
|
Revising Implemented CE's
|
|
1
|
985
|
16 November 2021
|
PMI after Completion Date
|
|
3
|
1710
|
16 November 2021
|
Lack of Site Access
|
|
1
|
409
|
16 November 2021
|
NEC3 option B - Compensation Event
|
|
1
|
556
|
9 November 2021
|
NEC3 ECC Option A - Delivery location of free issue materials
|
|
1
|
566
|
5 November 2021
|
C's Proposal used to Change WI
|
|
1
|
377
|
1 November 2021
|
EC Short Contract - Client's Liabilities
|
|
4
|
685
|
29 October 2021
|
NEC ECC: Clause 61.3 Failure to notify a compensation event within 8 weeks
|
|
3
|
1583
|
29 October 2021
|
ECS Understanding 60.7
|
|
2
|
342
|
28 October 2021
|
NEC 3 ECC - SSCC - Charges Inclusions
|
|
1
|
861
|
27 October 2021
|
NEC3 Option B, Clause 60.7
|
|
3
|
1146
|
26 October 2021
|
How are Statuatory Undertakers dealt with under the NEC3
|
|
1
|
647
|
18 October 2021
|
Early Warnings after Notification of Compensation Events
|
|
3
|
1419
|
15 October 2021
|
NEC4 Option B and Covid related material cost increases
|
|
1
|
545
|
12 October 2021
|
Movement of Sectional Completion Dates
|
|
3
|
654
|
11 October 2021
|
ECC Clause 60.4
|
|
7
|
1139
|
7 October 2021
|
Implementation of CE in NEC 4 Contract Option B
|
|
1
|
517
|
1 October 2021
|
NEC4 ESCS - Contractor Delay
|
|
1
|
447
|
28 September 2021
|
Concurrent delays both caused by Employer
|
|
3
|
540
|
28 September 2021
|
Unforeseen Ground Condition
|
|
2
|
590
|
27 September 2021
|
Temporary propping – scope change or contractors design?
|
|
3
|
533
|
23 September 2021
|
NEC ECC - Z clause that means working around existing services is excluded
|
|
2
|
496
|
22 September 2021
|
Ambit of PM authority in NEC3 from a time perspective
|
|
6
|
561
|
16 September 2021
|
Works Information (drawings)
|
|
2
|
580
|
9 September 2021
|
NEC 3 Option A Compensation Events
|
|
4
|
701
|
6 September 2021
|
Covid, X2 and Availability of Materials
|
|
2
|
680
|
24 August 2021
|