Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,331 questions

4,533 answers

597 comments

34,877 users

Register its Free

Download here

NEC3 ECC: What happens if Contractor volunteers to accelerate?

+1 vote
198 views
What happens in the rare situation where a Contractor decides to accelerate (small a) by his own accord? Looks to me like nothing happens other than planned Completion comes forward on the programme for acceptance and if realistic etc the Employer should accept. This is under an option C contract.
asked Apr 4, 2015 in NEC3 and NEC4 Contracts by Darren  
   

1 Answer

+1 vote
Yes that is pretty much it. Under option C both Parties share on any cost savings made due to finishing early, but don't forget they may have spent money to "speed up" (which hopefully was less than the prelims saved).

The Contractor would do this under any option to de-risk the project and to make it less likely they would incur delay damages. Planned Completion coming forward creates "terminal float" which the Contractor owns.
answered Apr 4, 2015 by Glenn Hide (33,710 points)