Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,522 questions

5,929 answers

1,332 comments

Register its Free

Download here

NEC3 ECC: Prioject Manager's failure to respond to a communication

+2 votes
1,416 views
If the Project Manager fails to respond to a communication, under clause 60.1 (6) we can notify a compensation event, is there any further recourse that can be taken should the Project Manager continue to fail to provide a response within the required time frame under the Contract ?
asked Mar 31, 2015 in Compensation Events by David Roche (960 points)  

1 Answer

+2 votes
 
Best answer
Under NEC3 contracts the Contractor's remedy for breach of contract is the compensation event mechanism.  Therefore as you have rightly identified you would raise a compensation event under 60.1(6).  

There are other actions you can take to increase the pressure on the Project Manager to respond.
1) Issue an early warning and instruct a risk reduction meeting under 16.2, or
2) Issue a revised programme under 32.2 showing the impact on the programme of the failure to respond (this assumes you haven't been instructed to submit a quotation for the breach).  This programme will, of course, show an impact on planned Completion...

The NEC3 brought in the deemed acceptance process for compensation events to deal with the 'indolent' Project Manager so when issuing your notices make sure you familiarise yourself with those provisions in 61.4, 62.6 and 64.4 and stick rigidly to them.
answered Apr 1, 2015 by John Rayner (2,720 points)